March- April 2006

  • 1
  • 2

Meeting the Challenges of Underground Construction

Some underground projects go smoothly, and others are a challenge. Dry sand may flow into your trench and require you to shore it quickly. Often, you have to fight water. You may have to drill and jack pipe more than 300 feet into the soil and then dig out the last few feet by hand because the drill rig can’t reach that far.

Article Tools

Create a Link to this Article

By Daniel C. Brown

Comments

Those are just a few of the problems solved by the contractors in the following stories. Flowing sand presents the challenge on the first project, Point of the Mountain Aqueduct in the Salt Lake City area. Contractor W.W. Clyde & Co. is installing 12 miles of 60-inch welded steel water pipe through both rural and residential areas.

“We have to maintain traffic and utilities through the corridor,” says Randy Lingwall, Clyde’s project manager. “We’re trenching and shoring the sections in the paved areas, but we can open-cut and slope the trench out in the sagebrush.”

At the peak of construction last summer, Clyde was running six different headings, each with two or three excavators. For a typical crew, a Caterpillar 385 excavator opened up the trench, a smaller excavator installs shoring, and a third ’hoe handles backfilling. Pipe depth ran between 10 and 29 feet, and the shored sections were 12 to 14 feet wide.

PHOTO: CLARK CONSTRUCTION
Complex shoring in underground site

Shoring has proven to be labor-intensive, because the fine sand flows so readily. “It’s like trying to dig a trench in water,” says Lingwall.

So Clyde went to United Rentals and bought slide rail shoring made by Efficiency Production Inc. The shoring consists of driven posts and panels that fit down between the posts, or rails. The excavator drives the rails into place at specified intervals. Laborers connect the posts and panels as construction proceeds. “It’s working as it was designed to work,” says Lingwall. “This shoring is the only thing we could find that would stop the sand from caving in, keep current utilities in place, and let us maintain a narrow excavation.”

Finished Early
Adding a second construction crew is helping The Industrial Company (TIC) complete a cut-and-cover box culvert job five months ahead of schedule in Savannah, GA. When it’s complete, the 1-mile-plus project will provide double and triple box culverts, and a stretch of concrete pipe, to drain stormwater that has often flooded this otherwise charming coastal city.

“The biggest factor behind finishing early was to start up with a second crew,” says Carl Kleeman III, vice president of TIC’s Savannah office. “We outfitted a whole second crew with John Deere equipment—two large excavators, a mini-excavator, a 544J loader, and a 450J bulldozer. Using just one crew would have taken another eight months.”

TIC used sheet piling in two parallel lines spaced 32 feet apart, to support the trench. Both the first and second crews excavate the trench with a John Deere 330CLC excavator. Working in shallower ground, the second crew has also used its excavator to drive sheet pile.

“The 330CLC works great with the pile hammer,” says Mark Waltz, TIC’s equipment manager. “It’s a lot faster to mount the pile hammer on an excavator than a crane, because we’ve got the hammer fitted with a quick coupler. He can drive pile, and then in about 20 seconds he can put the hammer in its stand, grab the bucket, and start excavating.”

After crews place bedding stone and build a 48-foot length of floor slab for the box culvert, a traveling concrete form moves into place. The form is shaped like an upside-down U for each box of the culvert. The form fits between the sheet pile and serves to build both the roof and the walls of the culvert in one pour.

Building a culvert down one street presented a challenge because of the narrow widths—essentially residential front lawns—located outside the sheet piling. Houses precluded driving concrete trucks alongside the sheet piling and dumping concrete into the forms. Instead, concrete trucks had to park at the forward edge of progress and then rely on a pump to move material back to the forms.

Deep Benching
For a sanitary sewer project near Rockford, IL, contractors are using both open-cut trenching and pipe-jacking methods. The project includes a total of 4,800 feet of heavy-walled PVC pipe of diameters varying among 18 inches, 15 inches, and 8 inches. “We had to go through an 1,800-foot distance where there’s a 35- or 36-foot cut,” says Steve Schlichting, one owner of the general contractor, Schlichting & Sons Excavating Inc.

“If we had a 35-foot cut, we’d first bench down 17 feet, but if we had a 26-foot cut, we’d only bench down 8 feet so that we had a constant 18-foot trench,” he says. “Then we’d come back and bench down 3 or 4 more feet. We had a 14-foot-high stacked trench box, with an 8-footer and a 6-footer. The excavator would hit pockets of sand and I’d have to back up and bench myself down, because the trench box would pull me back into the hole.

“Safety is the most important thing,” Schlichting says. “Because this trench is so deep, it’s all the more life-threatening.”

The project’s biggest challenge was the groundwater. “If you don’t get ahead of the water, it gets ahead of you,” says Schlichting. “If you let it get ahead, it’s fight, fight, fight the water.”

To dewater the trench, Schlichting put a 12-inch PVC pipe down into the ground at one manhole and pumped from that around the clock. At one time, the contractor also had two 2-inch pumps and one 3-inch pump inside the trench box to pump water out.

Advertisement

At a junction between the open-cut trench and one of the pipe-jacking lengths, Schlichting installed a four-sided Pro-Tec trench box that is 40 feet long, 10 feet wide, and 22 feet high. It works like slide rail shoring so that a side panel can raise up to allow pipe to be jacked into the bottom of the hole. “This way, we’re protected on four sides,” says Schlichting.

The pipe-jacking contractor, Central Boring, encountered difficulty with drilling one stretch at about 300 feet into the bore, Schlichting says. The drill kept hitting rocks and became ineffective at that distance, so the contractor had to dig out the last 40 feet by hand—and jackhammer the rocks out. To some extent the rocks were a surprise, Schlichting says. “Prior to that it was all bank-run sand and gravel. Then we hit hardpan and in some areas hit pockets of sand that had water in them.”

Next Page >
  • 1
  • 2

What Do You Think?

Post a Comment

Be the first to tell us what you think!

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get GX Contractor Email Updates!

Get weekly news and updates through our GX Contractor email newsletter!