March-April 2005

  • 1
  • 2

Creative Contractor Responds to Challenges at Branson Landing

Article Tools

Create a Link to this Article

By Richard Rybka

Comments

Creating new facilities to replace aging and outdated ones usually means working adjacent to geographic features and developed areas that limit access and add complications. These types of projects force a contractor to rely on his expertise and develop new strategies to overcome problems as they are encountered.

Branson, MO, has attracted travelers since the 1800s. Over the years, the pristine waters of Lake Taneycomo and the natural beauty of the Ozark Mountains have led fishermen and sightseers to this area. Today, Branson is one of America’s premier vacation travel destinations.

Originally, the White River flowed through the Branson area. In 1913, a power dam was built downstream, raising the water level and creating Lake Taneycomo. In 1958, Table Rock Lake was constructed upstream. Rock cliffs rise up on the southeastern side of the lake. A low floodplain remains on the northeastern side.

Branson’s downtown area extends to the shoreline of Lake Taneycomo. Railroad tracks following the water’s edge separate the historic town core from the lakefront area. As the town developed, recreational facilities were built along the river frontage. This area became the site for a city park, a municipal ball field, marinas, and campgrounds.

everal years ago, a major redevelopment of this lakefront area was proposed. A total of 95 acres with 1.5 miles of shoreline was acquired by HCW Development. The plans for Branson Landing include an extensive convention center, two hotels, a marina, Bass Pro Shops, waterfront condominiums, and a spectacular $9 million dollar fountain. Construction of the project finally began this spring, and is scheduled for completion in April 2006.

The Contractor
Tom Boyce founded his site work company in 1989. The company is located in Branson, but has traveled to Kansas, Tennessee, Arizona, and Arkansas to complete out-of-state projects for local clients. Over the years, Tom Boyce Excavating has grown to employ 65 people, including five project superintendents. Scott Klempel, vice president, and Travis McKenzie, estimator, work with Tom in managing the large number of projects the company completes each year. The company’s current workload includes four subdivisions, two townhouse/condominium sites, two tourist attraction sites, and a site prep/road improvements project 10 miles south of Branson at Big Cedar Wilderness Club.

Boyce realizes that maintaining this workload and pace requires tight organization and intelligent management. He hired Travis McKenzie earlier this year because of his experience with civil engineering firms. McKenzie’s responsibilities include estimating and overseeing layout for field operations. He is also involved in figuring the quantities and costs for change orders as they occur. Tom Boyce frequently offers suggestions to improve the way a project is constructed. As Travis McKenzie puts it, “There are too many unforeseen things underground that you just can’t anticipate. When we get in the field, there are things that will work better than what’s on paper.”

Site Challenges and Creative Solutions
Phase One of Branson Landing is located on a 35-acre portion of the total development tract. Site preparation for Phase One began in July 2004. The Killian/Turner joint venture team, of Springfield and Kansas City, MO, is general contractor for the entire project. Tom Boyce Excavating has been awarded the site work and utility subcontracts for Phase One that include demolition, mass grading for building pads, construction of 1,450 feet of utilities, 2,480 feet of 30-inch and 60-inch storm drainage pipe, 3,200 feet of perforated drain pipe, rock stabilization for extensive retaining walls, and curb/base for a contractor staging area.

Demolition of existing roadways, utilities, sidewalks, a municipal pool and baseball field, docks, and several buildings was the first construction task. After demolition was completed, Boyce prepared for filling operations. Topsoil was stripped from the site and stockpiled. To elevate the finished floor levels of the buildings above lake flood levels, approximately 300,000 cubic yards of imported fill material were required.

Photo: Tom Boyce

The exposed subgrade was inspected by the geotechnical engineers. The subgrade soils were too silty and organic—typical of soils found in river floodplains—to serve as a firm base. Nearly 100,000 cubic yards of unsuitable material was stockpiled on the site for removal at a later date.

Advertisement

The engineering plans and specifications called for select earth fill. Boyce looked ahead to the upcoming winter months when continuous operations would have to be maintained to meet the time schedule. He knew that earth fill would become waterlogged and site access would be difficult, if not impossible. Strategically, Boyce requested permission to use rock fill in place of earth. This guaranteed a firm working surface for future operations in the winter months.

Branson’s street layout presented a huge obstacle to trucking large volumes of material into and out of the site. The main street leading to Branson Landing comes down a long hill, with moderately steep grades in some areas. It travels through the heart of the downtown area, with narrow streets, passenger vehicles, and heavy pedestrian traffic. Branson's popularity as a tourist attraction creates car-stopping congestion, especially during the summer months. To avoid these conflicts and expedite operations, Boyce planned his trucking operations for the night hours between 7:00 p.m. and 7:00 a.m. when traffic was minimal.

Next Page >
  • 1
  • 2

What Do You Think?

Post a Comment

Be the first to tell us what you think!

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get GX Contractor Email Updates!

Get weekly news and updates through our GX Contractor email newsletter!